drow the network diagram and answers the following for the Q.1 , Check the attached pictures
Your project calendar is a 6-day week with Monday off.
Your project is due to start on Tuesday, May 25th.
July 1st, the first Monday in August, and the first Monday in September are nonworking days.
Develop a network diagram based on the above project data, including a proper legend and relationship arrows.
Determine the project critical path.
Fill in the blanks in the above table: ES in Base₁ and LF in Base₁
Determine the project completion calendar date.
Determine the task H Early starting ES calendar date.
Determine the task E Late LF finish calendar date.